The
Village at Torrey Pines, West
Opening
Fall 2009
Groundbreaking
for our newest housing endeavour took place October
1 on the northwest corner of campus, in Eleanor
Roosevelt College.
Scheduled
to open fall 2009, the Village at Torrey Pines
West will house more than 1,000 transfer students.
The project will include a 14-story high rise
as well as several three-story buildings. Upon
completion of the second phase to take place
later, the Village will house a total of 1,800
students.
The live•play•eat
facilities encompass 370,000
gross sq. ft. for student and staff
living units as well as a variety of retail
space including a satellite bookstore and a small
café,
administration offices, conference
facilities, laundry, mail room and other life-enhancing
amenities.
Just
click on the images below to see a larger view. Please
enable pop-ups in your browser.
Keep checking back
here for updated construction progress photos.
| Photos
from the Groundbreaking Ceremony |
CONSTRUCTION ALERT - The Village (North Campus Housing Phase 1)
Project Description/Location
The North Campus Housing project includes the construction of 8 buildings, totaling over 370,000 gross sq. ft. In addition to student and staff living units, the project includes administration offices, a satellite bookstore, conference facilities, a small café, laundry, mail room and other ancillary type spaces. The project is located on the North Campus area and will encompass the existing parking lots P-355 and P-356.
Immediate Street Impacts
Beginning in mid-September 2007 and continuing until July of 2009, vehicular traffic around the site and on adjacent streets will be impacted at times to accommodate construction activities and utility installation. There will be occasions when Scholars Drive North and portions of North Point Drive will be limited to one lane of traffic. During these times, flagmen will be present to direct traffic. Pedestrian sidewalks adjacent to the project site will remain open throughout the duration of the Project.
Please view the area map at: http://fdc.ucsd.edu/alerts/files/nocampusupdate.pdf
If you have any questions, please contact the Project Manager, Mark Rowland, at 858-822-0275, or Project Specialist, Nancy Sillman, at 858-534-2981. We greatly appreciate your patience during these construction activities. |